The largest area of the PFQ bank. Planning questions reward knowing what a plan is for: the project management plan is the baseline everything is measured against, built from estimates and the subsidiary management plans.
What planning covers in the PFQ
- The project management plan: purpose and what it brings together
- Estimating and why estimates carry uncertainty (the estimating funnel)
- Baselines, and re-planning through change control
- Deliverables, milestones and the schedule
- Assumptions, constraints and dependencies
Where candidates lose marks
Calling any document 'the plan' — the project management plan is a single, owned, baselined artefact.
Confusing an estimate with a target — estimates carry uncertainty.
Moving a baseline informally — a baseline only changes through change control.
Free, timed, exam-style questions across all ten PFQ topics — with an explanation for every answer and a per-topic breakdown.
Start a free practice testPlanning questions, answered
What is the project management plan?
The single, owned, baselined document that sets out how the project will be delivered — bringing together scope, schedule, cost, quality, risk and the other management plans. It is the baseline everything is measured against, not a folder of loose documents.
Why do estimates carry uncertainty?
Because early in a project little is known, so estimates are approximate and become more accurate as the project progresses — the estimating funnel. Treating an early estimate as a firm commitment is a common mistake.